The influence of related disciplines on project management practice

with one comment

Introduction

Project management is a relatively new discipline; one that has been formalized only in the last half century or so. Consequently, both academics and practitioners routinely draw upon knowledge in allied (or related)  disciplines in order to advance the theory and practice of project management.  Given this, it is of interest to ask:  what is the (current and future) influence of other, related disciplines on the profession of project management? A paper by Yoong Kwak and Frank Anbari entitled, Availability-Impact Analysis of Project Management Trends: Perspectives From Allied Disciplines, looks into this question.  This post is a summary and review of the paper.

Some terminology and assumptions first. An allied discipline, in the context of this paper,  is any discipline that is related to project management-  examples of this include Human Resource Management and Information Technology.  Availability is the volume of ideas relating to project management in an allied discipline and impact refers to the influence of that research on project management practice.  Note that availability and impact are treated as independent variables in the study.

Objectives, methodology and approach

The questions that Kwak and Anbari seek to answer are:

  • What trends in allied disciplines could have a significant effect on project management theory and practice?
  • How would these trends change (the theory and practice of) project management?
  • How would project managers have to change their mind-set because of the impact of these  disciplines?
  • What actions can be taken to meet the challenges posed by trends in allied disciplines?

Note that I have paraphrased their questions for clarity.

To answer these  question Kwak and Anbari surveyed a selected group of project managers and project management researchers, seeking their input on a range of issues relating to the above questions.    The surveys also solicited qualitative information through respondents’ opinions on the impact, trends and future of project management.  The italics in the previous sentence are intended to highlight the conclusions are based on subjective data gathered from a relatively homogeneous sample – more on this later in the review.

Based on the survey data, the authors:

  • Derived and plotted availability-impact relationships for each of the allied disciplines in a 2×2 matrix (in which each of the two variables took on the values ‘High’ and ‘Low’)
  • Identified how trends in these disciplines influence project management.
  • Conducted a structured survey to solicit opinions on how the project management community can respond to (or take advantage) of these influences.

By reviewing project management research literature, the authors identified the following eight allied areas as being potentially relevant to the future of the discipline:

  1. Operations Research/Decision Sciences/Operation Management/ Supply-Chain Management (abbreviated as OR/DS/OM/SCM)
  2. Organizational Behavior/Human Resource Management (abbreviated as OB/HR)
  3. Information Technology/Information Systems (IT/IS)
  4. Technology Applications/Innovation/New Product Development/Research and Development (TECH/INNOV/NPD/R&D)
  5. Engineering and Construction/Contracts/Legal Aspects/Expert Witness(EC/CONTRACT/LEGAL)
  6. Strategy/Integration/Portfolio Management/Value of Project Management/Marketing (STRATEGY/PPM)
  7. Performance Management/Earned Value Management/Project Finance and Accounting (PERFORM/EVM)
  8. Quality Management/Six Sigma/Process Improvement (QM/6SIGMA/PI)

I’m not an academic, and don’t claim to be current with research literature, but I think that psychology and economics ought to have made it to this list.

In the survey questionnaire, the authors asked respondents to rank  the above disciplines on a 7 point scale, for the following criteria:

  • The availability of project management-related information/knowledge/research in the discipline.
  • The impact of the discipline on project management.

The rating was done on an ordinal scale of 1 to 7.  Respondents were also asked open ended questions regarding trends in allied disciplines and how the project management community should adapt to or take advantage of these trends.

The authors describe the demographics of the survey population – I won’t go into details of this; please see the paper for details.

Results and Discussion

The current availability and impact of allied disciplines on project management – as perceived by the surveyed practitioners and academics –  is summarized in Figure 1 and the predicted future availability-impact relationships are shown in Figure 2.  I’ll discuss the current situation first.

Current Situation

The current situation is as shown below:

availability-impact

Figure 1: Current availability-impact of allied disciplines

According to the survey data, disciplines in the lower left quadrant are lacking in novel project management-related information and thus have potential for more research. They also do not have much of an impact on the field. In my opinion, even though there may be a lack of research directly related to project management  in these areas, there are plenty of papers whose findings can be adapted to project management – see  this post from an example drawn from a recent paper on strategy execution. My point: even research that isn’t directly related to project management can be relevant to the field.

Disciplines in lower right quadrant have plenty of research related to project management, but most of this work tends to have a low impact on the field. This seems reasonable– there’s a stack of research dealing with project performance and engineering/construction projects (this observation is based on a quick survey of papers that have appeared in the Project Management Journal over the last two years). Most of this research tends to have little effect on the field – for example, there haven’t been many radically new practices in the area of performance and construction management.

Disciplines in the upper left quadrant lack research but could potentially have a great impact on project management practice.  To me this quadrant presents interesting possibilities because it refers to areas which currently have no (or very little) project management-related research but which could, nevertheless,  have a high impact on practice. As described in my discussion of the low-low quadrant – a lot of research in other, unrelated fields  can be adapted to  project management.  Based on my readings, I believe behavioural science/psychology (focusing on the individual rather than the group) and economics fall into this category – as examples see this post for an example drawn from psychology and this one for one drawn from economics.  Unfortunately these fields are not considered by the authors.

This brings us to the upper right quadrant, which includes quality/process management and information technology. There’s little doubt that in recent years there’s been deluge of project-related research papers published in these areas. It is also clear that these areas have had a high impact on project management practice. However,  in my opinion, it is far from clear that the effect of this research has been positive ;  if anything it has lead to an unhealthy obsession with process and technology based approaches to project management.

Future situation

Future trends, according to those surveyed, are as depicted in Figure 2.

availability-impact2

Figure 2: Future availability-impact of allied disciplines

Let’s look at the disciplines that have moved:

PERFORM/EVM and STRATEGY/PPM have moved up to the high-high quadrant reflecting their (perceived) future importance. However, is this really the case or is it a case of availability bias? The latter is plausible, given the recent flood of papers,  articles and talks on topics relating to STRATEGY/PPM  in  journals and conferences. Practitioners and academics exposed to this constant barrage of information (propaganda?) on the topic cannot but help think that it must be a field of great relevance  The anticipated increase in importance of PERFORM/EVM, on the other hand, reflects the belief that project management will become more “metricised” or measurement-oriented.  This is no bad thing, providing the metrics are meaningful. In this connection, it is worth looking at Douglas Hubbard’s book  on the measurement of intangibles.

OR/DS/OM/SCM has moved from the lower left to the lower right quadrant reflecting the respondents’ perceptions that there will be more project management related research in these areas,  but that this research will continue to be of limited relevance to the profession.  On the surface, this seems quite plausible – as one of the respondents put it, “The impact of decision sciences on project management was high until the 1960s. Project management had its genesis in Operations Research. However, since the 1970s the relative importance, knowledge and research in this area has been decreasing [in comparison to other fields]…”  However, I’m not entirely convinced:  case can be made that radical advances in decision sciences may cause a reversal of this trend. The portents are already there – see Hubbard’s work on applied information economics, for example.

EC/CONTRACT/LEGAL has moved from the lower right to the lower left quadrant. I think this is quite possibly correct. Why? Well, because project management, ever since its inception, has been borrowing and adapting much from these areas. It is therefore only natural to expect that this will plateau out (if it hasn’t already)  and decrease as time goes on.

A note on relative availability and impact or IT/IS

From an analysis of the raw rankings of the disciplines, the authors infer that  IT/IS has, and will continue to have, an availability and impact that is much greater than  any other discipline. Presumably this is a consequence of IT/IS being ranked much higher on the 7 point scale than any of the other disciplines.  I can’t help but wonder if this is due to a bias in the surveyed population: if one interviews IT project managers or academics specializing in IT, it should be no surprise if they rate the accessibility and importance of technology as being much higher than that of other disciplines. Unfortunately Kwak and Anbari do not give a discipline-wise breakdown of the survey respondents, so I’m unable to judge if this is so.

Opinions of selected respondents

The authors also present detailed opinions of selected respondents.  On reading these I found nothing strikingly new. Two academics pleaded  for project management to be treated with more respect by other academics – i.e. be “recognized in the management faculty and accorded an equal status to with other traditional management science disciplines.” That academics are concerned about the status of the profession is only natural; whether this “equal status” is desirable is another matter altogether. Another researcher waxed eloquent on the effects of globalization and technology – trends that I think are evident to most practitioners.

The practitioners, on the other hand, focused on currently fashionable areas of practice: quality management/process improvement and portfolio management. There was also a mention of how a “project-based world” was needed in order to respond to “increasing complexity.”   The problem is that these terms mean different things to different people, consequently they don’t mean much at all (see this post for more on the confusion regarding  the term “complexity” in the context of projects).

Conclusion

The authors end with some general statements that they claim to have derived from the  survey data. These can  be summarized as follows:

1. OB/HR is becoming increasingly important as much of project work is about managing internal and external relationships. There is a growing recognition (finally!) that projects are more about people than processes.

2.  There will be an increasing dependence on software tools to manage projects. (IS/IT)

3, There will be an increasing focus on measuring performance and compliance with regulations and standards (PERFORM/EVM)

4. Portfolio management and quality/process improvement (STRATEGY/PPM and QM/6SIGMA/PI) will continue to get a lot of attention in industry.

5. New tools and techniques will emerge from the intersection between traditional management disciplines (OR/DS/OM/SCM and PERFORM/EVM) and newer ones (IT/IS and TECH/INNOV/NPD/R&D)

It isn’t entirely clear on what basis the authors make the above statements:  are they based on: 1) survey responses, 2)  research literature or 3) the authors’ opinions?   And, if it is the first:  can one make the above broad generalisations based on small surveys involving less than 100 respondents ? Perhaps not,  I think.

Finally the authors end with this plea

The project management profession is continuously evolving, so the project management community should be receptive to new ideas and also be sensitive to the yearning (!?) of the public and professional community so as to model project management practices to meet their expectations. “

This is true: the project management “community” remains fixated on classical practices and techniques,  many of which have questionable value. A degree of openness to new ideas and practices wouldn’t be amiss.

The paper attempts to gauge the current and future influence of allied fields on the research and practice of project management. It does so by surveying a sample of project management academics and professionals and making inferences based on the collected data. The sample is drawn from a population that is steeped in current practice and theory. As a result the respondents may not be aware of  the possibilities offered by fields that are currently not on the “project management radar.”  This might explain why the upper left quadrant is empty in both matrices.  To get around this the authors could have solicited the opinions of practitioners/theorists from allied disciplines.

To summarise: The authors infer some interesting trends from their data, but there remain some questions about the robustness of the inferences and the generalisations made from them.

Written by K

January 14, 2010 at 10:47 pm

Cooperation versus self-interest: the theory of collective action and its relevance to project management

with 6 comments

Introduction

Conventional wisdom deems that any organizational activity involving  several people has to be closely supervised to prevent it from dissolving into chaos and anarchy. The assumption underlying this view is that individuals involved in the activity will,  if left unsupervised,  make decisions based on self interest rather than the common good, and hence will invariably make the wrong decision as far as the collective enterprise is concerned. This assumption finds justification in rational choice theory, which predicts that individuals will act in ways that maximize their personal benefit without any regard to the common good. This view is exemplified in the so-called Tragedy of the Commons, where individuals who have access to a common resource over-exploit it in their pursuit of personal gain, and thus end up depleting the resource completely.  Fortunately, this view is demonstrably incorrect: the work of Elinor Ostrom, one of the 2009 Nobel prize winners for Economics, shows that, given the right conditions, groups can work towards the common good even if it means forgoing personal gains. This post is a brief look into Ostrom’s work and the insights it offers into the theory and practice of project management.

Background: rationality, bounded rationality and theories of choice

Classical economics assumes that individuals’ actions are driven by rational self-interest – i.e. the well-known “what’s in it for me” factor (this is one of the assumptions of rational choice theory).  So, in a situation where an individual has access to a resource that is also available to others, classical economics predicts that the individual will aim to maximize his or her benefit without any regard to the common good. Clearly, the group will achieve much better results as a whole if it were to exploit the resource in a cooperative way. There are several real-world examples where such cooperative behaviour has been successful in achieving outcomes for the common good (see this paper for some). However, according to classical economic theory, such cooperative behaviour is simply not possible.

So, what’s wrong with rational choice theory?

A couple of things, at least:

Firstly, implicit in rational choice theory is the assumption that individuals can figure out the best choice in any given situation.  This is obviously incorrect. As Ostrom has stated in one of her papers:

Because individuals are boundedly rational, they do not calculate a complete set of strategies for every situation they face. Few situations in life generate information about all potential actions that one can take, all outcomes that can be obtained, and all strategies that others can take.

Instead, they use heuristics (experienced-based methods), norms (value-based techniques) and rules (mutually agreed regulations) to arrive at “good enough” decisions.  Note that Ostrom makes a distinction between norms and rules, the former being implicit (unstated) rules, which are determined by the cultural attitudes and values)

Secondly, rational choice theory assumes that humans behave as self-centered, short-term maximisers. Such theories – which assume that humans act solely out of self interest – work in competitive situations (such as the stock-market) but do not work in situations in which collective action is called for.

Ostrom’s work essentially addresses the shortcomings of rational choice theory.

A behavioural approach

Ostrom’s work looks at how groups act collectively to solve social dilemmas such as the one implicit in the tragedy of the commons. To quote from this post by Umair Haque:

…Ostrom’s work is concerned, fundamentally, with challenging Garret Hardin’s famous, Tragedy of the Commons [Note: Hardin’s article can be accessed here], itself a living expression of neoclassical thinking. Ostrom suggests that far from a tragedy, the commons can be managed from the bottom-up for a shared prosperity — given the right institutions….

In a paper entitled, A Behavioral Approach to the Rational Choice Theory of Collective Action, published in 1998, Ostrom states that:

…much of our current public policy analysis is based on an assumption that rational individuals are helplessly trapped in social dilemmas from which they cannot extract themselves without inducement or sanctions applied from the outside. Many policies based on this assumption have been subject to major failure and have exacerbated the very problems they were in-tended to ameliorate. Policies based on the assumptions that individuals can learn how to devise well-tailored rules and cooperate conditionally when they participate in the design of institutions affecting them are more successful in the field…[Note:  see this book by Baland and Platteau, for example]

Rational choice works well in highly competitive situations such as the stock market, where personal gain is the whole aim of the game. However, it does not work in situations that demand collective action – and Ostrom presents some very general evidence to back this claim.

More interesting than the refutation of rational choice theory, though, is Ostrom’s discussion of the ways in which individuals “trapped” in social dilemmas end up making the right choices. In particular she singles out two empirically grounded ways in which individuals work towards outcomes that are much better than those offered by rational choice theory. These are:

Communication: In the rational view, communication makes no difference to the outcome.  That is, even if individuals make promises and commitments to each other (through communication), they will invariably break these for the sake of personal gain …or so the theory goes. In real life, however, it has been found that opportunities for communication significantly raise the cooperation rate in collective efforts (see this paper abstract or this one, for example). Moreover, research shows that face-to-face is far superior to any other form of communication, and that the main benefit achieved through communication is exchanging mutual commitment (“I promise to do this if you’ll promise to do that”) and increasing trust between individuals. It is interesting that the main role of communication is to enhance the relationship between individuals rather than to transfer information.

Innovative Governance:  Communication by itself may not be enough; there must be consequences for those who break promises and commitments. Accordingly, cooperation can be encouraged by implementing mutually accepted rules for individual conduct, and imposing sanctions on those who violate them. This effectively amounts to designing and implementing novel governance structures for the activity. Note that this must be done by the group; rules thrust upon the group by an external authority are unlikely to work.

Ostrom also identifies three core relationships that promote cooperation. These are:

Reciprocity: this refers to a family of strategies that are based on the expectation that people will respond to each other in kind – i.e. that they will do unto others as others do unto them.  In group situations, reciprocity can be a very effective means to promote and sustain cooperative behaviour.

Reputation: This refers to the general view of others towards a person. As such, reputation is a part of how others perceive a person, so it forms a part of the identity of the person in question. In situations demanding collective action, people might make judgements on a person’s reliability and trustworthiness based on his or her reputation.

Trust: Trust refers to expectations regarding others’ responses in situations where one has to act before others. Clearly, trust is an important factor in situations where others have to rely on others to do the right thing.

She describes reciprocity, reputation and trust as being central to a behavioural explanation of collective action:

…Thus, at the core of a behavioral explanation (of cooperative action) are the links between the trust that individuals have in others, the investment others make in trustworthy reputations, and the probability that participants will use reciprocity norms…

According to Ostrom, face-to-face communication and innovative governance can change the structure of dysfunctional collective situations by providing those involved with opportunities to enhance these core relationships. On the flip side, heavy-handed interventions and increased competition between individuals will to reduce them.

Implications for the practice of project management

Projects are temporary organisations set up in order to achieve specified objectives. Achieving these objectives typically requires collective and coordinated action.  Although project team members work within more or less structured (and often rigid) environments, how individuals work and interact with others on the team is still largely a matter of personal choice.  It is thus reasonable to expect that some aspects of theories of choice will be relevant to project situations.

The importance of communication in projects cannot be overstated. Many project failures can be attributed to a breakdown of communication, particularly at project interfaces (see my post on obstacles to project communication for more on this), Ostrom’s work reiterates the importance of communication, specifically emphasizing the need for face-to-face interactions. From experience I can vouch for the efficacy of face-to-face communication in defusing crises and clearing up misunderstandings.

In most project environments, governance is imposed by management. Most organisations have follow methodologies which have excruciatingly detailed prescriptions on how projects should be controlled and managed. Ostrom’s work suggests that a “light hand on the tiller” may work better. Such a view is supported by research in organisational theory (see my post on project management in post-bureaucratic organisations for example).  If a particular project control doesn’t work well or is too intrusive, change it. Better yet, seek the team’s input on what changes should be made. In fact, most methodologies give practitioners the latitude to customize processes to suit their environments. Unfortunately many organisations fail to take advantage of this flexibility, and consequently many project managers come to believe that control-oriented governance is the be all and end all of their job descriptions. Is it any wonder that project teams often complain about unnecessary bureaucracy getting in the way of work?

Finally, it isn’t hard to argue that the core relationships of reciprocity, reputation and trust would serve project teams just as well as they do other collectives. Teams in which individuals help each other (reciprocity), are aware of each others’ strengths (reputation) and know that they can rely on others if they need to (trust), not only have a better chance of success, but also make for a less stressful work environment. Unfortunately these relationships have long been dismissed by project rationalists as “warm and fuzzy” fluff, but perhaps the recognition of these in mainstream economic thought will  change that.

Concluding remarks

Classical theories of choice are based on the assumption that those making choices are rational and that they make decisions based on narrow self interest. These theories, which assume the best (rationality) and worst (self-interest) in humans, invariably yield pessimistic predictions when applied to situations that demand collective action. This is often used to justify external interventions aimed at imposing rules and enforcing cooperation, thus perpetuating a pessimistic view of the rational but selfish individual.  Ostrom’s work – which uses a mix of fieldwork, experiment, model building and theorizing –  highlights the flaws in theory of rational choice,  and shows how cooperative action is indeed possible, providing certain important relationships are fostered through internal communication and governance. Externally imposed edicts, rules and structures are largely unnecessary, and may even be counterproductive.

Projects are essentially cooperative endeavours. Given this, it is reasonable to expect that many of Ostrom’s insights into the conditions required for individuals to cooperate should apply to project environments.  My main aim in this post was to describe some elements of Ostrom’s prize-winning work and how they apply to project management. I hope that the points I’ve made are plausible, if not wholly convincing. And even if they aren’t, I hope this post has got you thinking about ways to increase cooperation within your project team.

Written by K

December 2, 2009 at 10:09 pm

Reasons and rationales for not managing risks on IT projects – a paper review

with 7 comments

Introduction

Anticipating and dealing with risks is an important part of managing projects. So much so that most frameworks and methodologies devote a fair bit of attention to risk management:  for example, the PMI framework considers risk management to be one of the nine “knowledge areas” of project management.  Now, frameworks and methodologies are normative– that is. they us how risks should be managed – but they don’t say anything about how are risks actually handled on projects.   It is perhaps too much  expect that all projects are run with  the full machinery of  formal risk management, but it is reasonable to  expect that most project managers deal with risks in some more or less systematic way.  However, project management lore is rife with stories of projects on which risks were managed inadequately, or not managed at all (see this post for some pertinent case studies).  This begs the question:  are there rational reasons for not managing risks on projects?    A paper by Elmar Kutsch and Mark Hall entitled, The Rational Choice of Not Applying Project Risk Management in Information Technology Projects,  addresses this question.   This post is a summary and review of the paper.

Background

The paper begins with a brief overview of risk management as prescribed by various standards. Risk management is about making decisions in the face of uncertainty. To make the right decisions, project managers need to figure out which risks are the most significant. Consequently, most methodologies offer techniques to rank risks based on various criteria.  These techniques are based on many (rather strong) assumptions, which the authors summarise as follows:

  1. An unambiguous identification of the problem (or risk) including its cause
  2. Perfect information about all relevant variables that affect the risk.
  3. A model of the risk that incorporates the aforementioned variables.
  4. A complete list of possible approaches to tackle the risks.
  5. An unambiguous, quantitative and internally consistent measure for the outcomes of each approach.
  6. Perfect knowledge of the consequences of each approach.
  7. Availability of resources for the successful implementation of the chosen solution.
  8. The presence of rational decision-makers (i.e. folks free from cognitive bias for example)

Most formal methodologies assume the above to be “self-evidently correct” (note that some of them aren’t correct, see my  posts on cognitive biases as project meta-risks and the limitations of scoring methods in risk analysis for more). Anyway, regardless of the validity of the assumptions,  it is clear that achieving all the above would require a great deal of commitment, effort and money.    This, according to the authors,  provides a hint as to why many projects are run without formal risk management. In their words:

…despite the existence of a self-evidently correct process to manage  project risk, some evidence suggests that project managers feel restricted in applying such an “optimal” process to manage risks. For example, Lyons and Skitmore (2004) investigated factors limiting the implementation of risk management in Australian construction projects. Similar findings about the barriers of using risk management in three Hong Kong industries were found in a further prominent study by Tummala, Leung, Burchett, and Leung (1997). The most dominant factors for constraining the use of project risk management are the lack of time, the problem of justifying the effort into project risk management, and the lack of information required to quantify/qualify risk estimates.

The authors review the research literature to find other factors that could reduce the likelihood of risk management being applied in projects. Based on their findings, they suggest the following as reasons  that project managers often offer as  justifications (or rationales)  for not managing risks:

  1. The problem of hindsight: Most risk management methodologies rely on historical data to calculate probabilities of risk eventuation. However, many managers feel they cannot rely on such data for their specific (unique) project.
  2. The problem of ownership: Risks are often thought of as “someone else’s problem”. There is often a reluctance to take ownership of a risk because of the fear of blame in case the risk response fails to address the risk.
  3. The problem of cost justification: From the premises listed above it is clear that proper risk management is a time-consuming, effort-laden and expensive process. Many IT projects are run on tight budgets, and risk management is an area that’s perceived as being an unnecessary expense.
  4. Lack of expertise: Project managers might be unaware of risk management technique.  I find this hard to believe, given that practically all textbooks and methodologies yammer on,  at great length, about the importance of managing risks. Besides, it is a pretty weak justification!
  5. The problem of anxiety:  By definition, risk management implies that one is considering things that can go wrong.  Sometimes, when informed about risks, stakeholders may decide not to go ahead with a project. Consequently, project managers may limit their risk identification efforts in an attempt to avoid making stakeholders nervous.

When justifying the decision not to manage risks, the above factors are often presented as barriers or problems which prevent the project manager from using risk management. As an illustration of (5) above, a project manager might say, “I can’t talk about risks on my project because the sponsor will freak out and throw me out of his office.”

Research Method

The authors started with an exploratory study aimed at developing an understanding of the problem from the perspective of IT project managers – i.e. how project managers actually experience the application of risk management on their projects. This study was done through face-to-face interviews. Based on patterns that emerged from this study, the authors developed a web-based survey that was administered to a wider group of project managers. The exploratory phase involved eighteen project managers whereas the in-depth survey was completed by just over a hundred  project managers all of whom were members of the PMI Risk Management Special Interest Group. Although the paper doesn’t say so, I assume that project managers were asked questions in reference to a specific project they were involved in (perhaps the most recent one?).

I won’t dwell any more on the research methodology;  the paper has all the  details.

Results and interpretation

Four of the eighteen project managers interviewed in the exploratory study did not apply risk management processes on their projects. The reasons given were interpreted by the authors as cost justification, hindsight and anxiety. I’ve italicized the word “interpreted” in the previous sentence because I believe the responses given by the project managers could just as easily be interpreted another way. I’ve presented their arguments below so that readers can judge for themselves.

One interviewee mentioned that, “At the beginning, we had so much to do that no one gave a thought to tackling risks. It  simply did not happen.” The authors conclude that the rationale for not managing risks in this case is one of cost justification, the chain of logic being that due to the lack of time, investment of resources in managing risks was not justified. To me this seems to read too much into the response. From the response it appears to me that the real reason is exactly what the interviewee states –  “no one thought of managing risks” – i.e. risks were  overlooked.

Another interviewee stated, “It would have been nice to do it differently, but because we were quite vulnerable in terms of software development, and because most of that was driven by the States, we were never in a position to be proactive. The Americans would say “We got an update to that system and we just released it to you,” rather than telling us a week in advance that something was happening. We were never ahead enough to be able to plan.” The authors interpret the lack of risk management in the this case as being due to the problem of hindsight – i.e.  because the risk that an update poses to other parts of the system could not have been anticipated, no risk management was possible. To me this interpretation seems a little thin – surely, most project managers understand the risks that arbitrary updates pose. From the response it appears that the real reason was that the project manager was not able to plan ahead because he/she had no advance warning of updates. This seems more a problem of a broken project management process rather than anything to do with risk management or hindsight. My point: the uncertainty here was known (high probability of regular updates),  so something could (and should) have been done about it whilst planning the project.

I’ve dwelt on these examples because it appears that the authors may have occasionally fallen into the trap of pigeon holing interviewee responses into their predefined rationales (the ones discussed in the previous section)  instead of listening to what was actually being said.  Of course, my impression is based on a reading of the paper and the data presented therein. The authors may well have other (unpublished) information to support their classification of interviewee responses. However, if that is the case, they should have presented the data in the paper  because the reliability of the second survey  depends on the set of predefined rationales being comprehensive  and correct.

The authors present a short discussion of the second phase of their study. They find that no formal risk management processes were used in about one third of the 102 cases studied. As the authors point out, that in itself is an interesting statistic, especially considering the money at stake in typical IT projects. In cases where no risk management was applied, respondents were asked to provide reasons why this was so. The reasons given were extremely varied but, once again, the authors pigeon-holed these into their predefined categories. I present some of the original responses and interpretations below so that readers can judge for themselves.

Consider the following reasons that were offered (by respondents) for not applying risk management:

  1. We haven’t got time left.”
  2. No executive call for risk measurements.”
  3. Company doesn’t see the value in adding the additional cycles to a project.” (?)
  4. Upper management did not think it required it.”
  5. Ignorance that such a thing was necessary.”
  6. An initial risk analysis was done, but the PM did not bother to follow up.”
  7. A single risk identification workshop was held early in the project before my arrival. Reason for not following the process was most probably the attitude of the members of the team.”

Interestingly, the authors interpret all the above responses (and a few more ) as being attributable to the cost justification rationale. However, it seems to me that there could be several other (more likely) interpretations.  For example: 2, 3, 4, 5 could be attributed to a lack of knowledge about the value of managing risks whereas 1, 6, 7 sound more like simple (and unfortunately, rather common!)  buck-passing.

Conclusion

Towards the end of the paper   the authors make an excellent point about the  rationality of a decision not to apply risk management. From the perspective of formal methodoologies such a decision is irrational. However, rationality (or the lack of it) isn’t so cut and dried. Here’s what the authors say:

…a decision by an IT project manager not to apply project risk management may be described as irrational, at least if one accepts the premise that the project manager chose not to apply a “self-evidently” correct process to optimally reduce the impact of risk on the project outcome. On the other hand, … a person who focuses only on the statistical probability of threats and their impacts and ignores any other information would be truly irrational. Hence, a project manager would act sensibly by, for example, not applying project risk management because he or she rates the utility of not using project risk management as higher than the utility of confronting stakeholders with discomforting information….”

…or spending money to address issues that may not eventuate, for that matter. The point being  that people don’t make decisions based on prescribed processes and procedures alone; there are other considerations.

The authors then go on to say,

PMI and APM claim that through the systematic identification, analysis, and response to risk, project managers can achieve the planned project outcome. However, the findings show that in more than one-third of all projects, the effectiveness of project risk management is virtually nonexistent because no formal project risk management process was applied due to the problem of cost justification.

Now, although it is undeniable that many projects are run with no risk management whatsoever,  I’m not sure I agree with the last statement in the quote. From the data presented in the paper, it seems more likely that a lack of knowledge  and “buck-passing”  are the prime reasons  for risk management being given short shrift on the projects surveyed. Even if cost justification was  offered as a rationale by some  interviewees,  their quotes suggest that the real reasons were quite different. This isn’t surprising: it is but natural  to attribute to unacceptable costs that which should be attributed to oversight or failure.  I think this may be the case in a large number of projects on which risks aren’t managed. However,  as the authors mention, it is impossible to make any generalisations based on small samples .  So, although it is incontrovertible that there are a significant number of projects on which risks aren’t managed, why this is so remains an open question.

Written by K